The B&B team was contracted by El Paso Water to provide preliminary design, final design, and construction phase services for a multiple lift station phase project. Phases III to IV consisted of eleven duplex lift stations ranging in size from 200-GPM to 600-GPM and six triplex lift stations ranging in size from 900-GPM to 1,400 GPM. These seventeen lift stations were successfully designed and constructed. During Phase VII, a pre-design report was completed on an additional seven lift stations. The project included complete electrical control upgrades, SCADA adaptation, and the introduction of odor control units for future connections. This multi-phased project consisted of the research and rehabilitation of over 17 submersible wastewater pumping stations ranging from 5-hp to 75-hp pumps.