Brock and Bustillos Inc. was contracted by the City of El Paso under an On-Call Construction Management Contract to provide construction management and RPR services for a street and drainage improvement project. The project involved the reconstruction of Princeton Street from Tulane to Greggerson and Valley View from Yarbrough to Greggerson. This project affected approximately one mile of streets in the Shawver Park neighborhood of District 7. Major stormwater improvements included the much-needed installation of 24-inch, 30-inch, and 36-inch reinforced concrete pipe (RCP) with the inclusion of a ponding area and the installation of additional drainage facilities. Having been selected to oversee construction management services, B&B assumed primary responsibility day-to-day project management and oversight, including consulting with and advising the Owner on resolutions of problems due to encountered field conditions, the review of shop drawings and submittals from the contractor for compliance with design concepts. B&B reviewed, prepared, and negotiated change order costs, performed the final inspection of the project, recommended acceptance, and provided a closeout package to the Owner. 

Project Details

  • Completion Date: March 2020 

  • Initial Construction Cost: $4,527,041.00 

  • Final Construction Cost: $1,015,300.65 

Before

During